Looks like you are not TradeKey.com's Member yet. Signup now to connect with over 10 Million Importers & Exporters globally.
Join Now, its Free |
BOOK A CALL
Book Call On Your Favorite Time

By Signing Up. I agree to TradeKey.com Terms of Use, Privacy Policy, IPR and receive emails related to our services

Contact Us
product
Prev
TZ1600-35 2-Sides 2-Coatings Aluminium Production Line (Separated)
Next

TZ1600-35 2-Sides 2-Coatings Aluminium Production Line (Separated)

FOB Price

Get Latest Price

|

- Minimum Order

Country:

China

Model No:

-

FOB Price:

Get Latest Price

Place of Origin:

China

Price for Minimum Order:

-

Minimum Order Quantity:

-

Packaging Detail:

-

Delivery Time:

65-120days

Supplying Ability:

-

Payment Type:

-

Product Group :

-

Contact Now
Free Member

Contact Person Chris Jiang

Foshan, Guangdong

Contact Now

Product Specification

Product Description

TZ******5 *-Sides *-Coatings Aluminium Production Line (Separated)
Coating line features:
Model TZ******5 coating line (separated structure) is suitable for certain coating factories. *-sides *-coating coating products in thickness range 0.*5mm~0.6mm applies to most ACP material, roofing and ceiling material. Model TZ******5 coating line is high quality coating line, good performance in all kinds of paint coating. Separated structure is flexible in production, pretreatment process and coating process are separated and non-interfering, so that production is much easier to plan or schedule. Operation faults and equipment problems effect is less.
A primary reason to choose separated structure is its advantage over dimension, Model TZ******5 requires only *5m×*8m×7m workshop.
Application: For coating aluminium coil of ACP(Aluminium Composite Panel), roofing , cladding, ceiling,roller shutter,etc.
Advantage: Widely usage range, short line, smaller dimension workshop needed,  less operation faults and equipment problems effect .
1. Main parameters of coating line
Material parameter
Thickness: 0.*5~0.6mm
Width: ***0mm
Outer diameter OD(max): Φ***0mm
Inner diameter: Φ**5mm
Bobbin material: Steel or paper
Inverval-layers deviation tolerance: ≤0.8 mm (Excluding the bottom 5 layers and exterior 2 layers)
Coil over-all deviation tolerance: ≤2 mm (Excluding the bottom 5 layers and exterior 2 layers)
Coating thickness: Dry film thickness: 8~*0 um
 
Product Weight: Max ***0kg(Excluding bobbin)
 
CCL Processing Speed: *5 m/min (Speed benchmark: thickness 0.*5mm coil exclude PVDF coating)
 
Heating Energy Source: LNG, LPG
 
Roller coating Process: Continuous 2 sides 2 coating & 2 baking
 
Properties and features:
Roller width: ***0mm
Coils feeding centering adjustment : ±*5mm
Threading speed: 5~*5m/min(Adjustable)
Line maximum speed: *5m/min
Line speed accuracy: Steady Speed, ±0.1%; Acceleration, ±0.4%
Uncoiling tension range: **0~**0kgf
Processing tension range: **0~**0kgf
Coiling tension range: **0~***0kgf
Tension accuracy: Steady Speed, ±1.0%; Acceleration, ±2.0%
Line space dimensions: ****0mm×***0mm×***0mm
Heating Energy Source: LNG, LPG
 
2. Basic Production Process
Coating line
Coil loading → Uncoil machine → Sewing table → Topside primer-paint roller-coater → Curing oven 1 → Air cooling → CPC 1 → Tension device 1 →Topside *-coat and backside roller-coater → Curing oven 2 → CPC 2 → Tension device 2 → Coil machiner → Coil discharging
 
Pretreatment line
Coil loading → Uncoil machine → Sewing table → Acid washing, brushing roller → Water washing → Deionized water washing → Drying → Roller-coating chromizing → Drying → Cooling → Tension device → Coil machine → Coil discharging
 
Rewinding line
Coil loading → Uncoil machine → Sewing table → Tension device → Coil machine → Coil discharging
 
3. Main devices list
Name Quantity
Uncoil machine 3
Sewing table 3
Tension Device 4
Redirection steel roller *1
Brushing roller 2
Degrease pool 3
Water washing pool 2
Drying device 2
Squeeze roller 5
Roller-coating chromizing coater 1
Coater 2
Curing oven 2
Heat system 2
Air cooling system 4
Film device 1
Coil machine 3
CPC 2
EPC 3
Steel frame 1
Electrical system 3
*Optional configuration: waste gas treatment and energy recycle system
 
4. Water and power consumption of coating line
Total power consumption: **0KW
Compressed air: Min5.5bar,1Nm3/min,actual consumption
Water: Deionized water, supply quantity is about 4T/h
Heating fuel: LPG or LNG
LPG consumption: 0.6 CBM/min
LNG consumption: 1 CBM/min
5.The coating line design and manufacture leads **0 days, installation and testing leads *0 days.
6.Trade terms: FOB, CIF are available
7.Payment terms: T/T, D/P, LC are acceptable
8. Packing style: Wooden pallet
9. Transportation: by sea
 

Country: China
Model No: -
FOB Price: Get Latest Price
Place of Origin: China
Price for Minimum Order: -
Minimum Order Quantity: -
Packaging Detail: -
Delivery Time: 65-120days
Supplying Ability: -
Payment Type: -
Product Group : -

Send a direct inquiry to this supplier

To:

Chris Jiang < Guangdong Litong Environmental Protection Machinery Co., Ltd. >

I want to know: